PORTFOLIO

Title:    Chaplin Court Infrastructure   Development Project

Client: ExxonMobil Cooperative         Society (EMCOOP)

Location: Ogombo, Lagos, Lagos        State Nigeria.

Duration: 4 years

Background: Road Construction, Drain Line Construction, Culvert Construction, Perimeter Fencing, Electrification and Water Reticulation.

Scope:  Project Set-up & Organisational Design, Project & Portfolio Management, Project Management & Delivery, Project Assurance & Governance.

Benefits: New urban settlement, secured and serene environment, with great facility for new Occupants.

Title: Ikom-Obudu Road Construction Project / Cross River State Road Construction Project

Client: Federal Government of            Nigeria, Cross River State

Location: Cross River State, Nigeria

Duration: 2 years

Background: The programme include 2 sections of the Federal Road (Ikom – Obudu Road, and Obudu  – Ranch Resort; total  rehabilitation) and 1 section of the State Road (Okundi-Nsadop Boje Road; partial  rehabilitation – surface dressing). Road Paving as a subcontract from a private company (Beebosco Road and Akai Street, Calabar – Asphalt paving/laying)

Scope:  Project Set-up & Organisational Design, Construction Management, Project Controls, Project Management & Delivery, Project Assurance & Governance.

Benefits: Eased travel time (Federal       Roads), gave open access to farms (Farm Road) and reduced accidents occasioned by bad road

Title:     Katsina –Ala – Wukari    Road Construction Project

Client:  Federal Road Maintenance         Agency (FERMA)

Location: Benue State to Taraba State, Nigeria

Duration: 4 months

Background: The project include 1 section of partial rehabilitation (Katsina – Ala to Wukari )

Scope:  Project Set-up & Organisational Design, Construction Management, Project Controls, Project Management & Delivery, Project Assurance & Governance.

Benefits: Eased travel time (Federal Roads) and reduced accidents occasioned by bad road.

Title:    1,000 Branches Rollout Project

Client: United Bank for Africa (UBA) PLC

Location: Across Nigeria

Duration: 2 years

Background: Construction of Bank offices, Bank standard finishing, instrumentation, and, Perimeter Fencing.

Scope:  Project Set-up, Project & Portfolio Management, Project Management & Delivery, Project Assurance & Governance.

Benefits: Customers’ access to more UBA Branches, and ease of banking

Title:    Bank Development Project

Client: Oceanic Bank International PLC

Location: Across Nigeria

Duration: 2 years

Background: Construction of Bank offices, Bank standard finishing, instrumentation, and, Perimeter Fencing

Scope:  Project Set-up, Project & Portfolio Management, Project Management & Delivery, Project Assurance & Governance.

Benefits: Customers’ access to more Oceanic Bank Branches, and ease of banking.

Title:    Security Upgrade Project (Part of Major Integrity Projects – MIPs)

Client: Confidential

Location: South-South, Nigeria

Duration: 3 Years

Background: Power Gate Installation, High-Tech Perimeter Fencing, Watch Tower Installation, Road Construction, Building Construction, Instrumentation, and Electrical Works

Scope:  Construction Management, Project Controls, Project Management & Delivery, Project Assurance & Governance.

Benefits: Security of Expatriates, security of Oil & Gas assets within the terminal, and the Guest House

Title:   Morecambe Hub Brownfield   Modification Projects Delivery.

Client:  Spirit Energy

Location:  East Irish Sea, Barrow-in Furness

Duration:  2 years

Background: Delivering a programme of over   60 brownfield modification   projects executed over 12 assets,   including 8 offshore and 4   onshore facilities.   Managed   Engineering, Construction and   Project Support contracts.

Scope:  Project & Portfolio Management,   Project Management & Delivery,   Project Set-up & Organisational   Design, Project Services, Project   Assurance & Governance, Benefits   Realisation Management.

Benefits:  100% of Modification Projects   completed right first time; Completed   70% of legacy projects (dating back   5 years); Development of new   assurance & governance process.

Title:   North Sea Field Development   Projects

Client:  Centrica Exploration & Production

Location:  Southern, Central, Northern North   Sea & West of Shetland

Duration:  4 years

Background: Delivering a programme of 5    North Sea field developments at   different project pre-sanction phases.

Scope:  Project & Portfolio Management,   Project Management & Delivery,   Project Set-up & Organisational   Design, Project Services, Project   Assurance & Governance, Project   Economics Analysis.

Benefits:  Generated 35% savings in project   investment costs; Streamlined   execution contractual strategy based   on novel technology introduction.

Title:   Cygnus Field Development Plan

Client:  Gas De France Suez UK E&P

Location:  Southern North Sea

Duration:  10 months

Background: Generation of the Cygnus Field   (proven & probable field reserves of   1.1 TCF) Development Plan for Final   Investment Decision by Field owners   Investment committee.

Scope:  Project Management & Delivery,   Project Services, Project   Assurance &   Governance, Project Economics   Analysis.

Benefits:  Value Engineered and evaluated a   new development scope that   achieved Final Investment Decision.

Title:   Viking Above Ground Gas Storage   Facility Project.

Client:  BP, Dong Energy & Gazprom JV

Location:  Etzel, Germany

Duration:  2 years

Background: Delivering a midstream (gas   dehydration & compression facilities)   and gas storage (underground salt   caverns) in Northern Germany to   address ullage in the European Gas   Supply Network.

Scope:  Project Management & Delivery,   Project Services, Project   Assurance &   Governance.

Benefits:  Projects completed 2 months ahead   of schedule.  Project yielded 5% cost   savings in compression installation   scope.

Title:    Hyatt Place (Hotel) Construction

Client: Confidential

Location: Main Street, Moncton, New Brunswick, Canada

Duration: 2 years

Background: Hotel Building Construction, Road Paving, Drain Line Construction, Culvert Construction, Perimeter Fencing

Scope:  Project Set-up & Organisational, Design, Project & Portfolio Management, Project Management & Delivery, Project Assurance & Governance.

Benefits: New quality hotel to complement the newly built Event Center.

Coming soon…